SGR Procurement Case

A challenge to the legality and constitutionality of the construction of the Standard Gauge Railway | Nairobi High Court Petition No. 58 of 2015 consolidated with Petition No. 209 of 2014 | Civil Appeal No. 13 of 2015 Court of Appeal at Nairobi Consolidated with Civil Appeal No. 10 of 2015
Case filed: Feb 2014Current status: Concluded (judgment Nov. 2014; appeal judgment June 2020)

Petitioners / Appellants

  • Okiya Omtatah Okoiti
  • Wyclife Gisebe Nyakina
  • The Law Society of Kenya

Respondents

  • The Attorney General

  • Kenya Railways Corporation

  • The Public Procurement Oversight Authority

  • China Road and Bridge Corporation

Current status

19 June 2020: Case concluded

The Court of Appeal ruled against the petitioners in its final judgment on 19 June 2020, concluding this case. See below for summary.

The High Court’s judgment of 21 November 2014, which also ruled against the petitioners, is available here.

Summary of facts & issues

This case arose out of the construction of the Standard Gauge Railway from Mombasa to Nairobi. The Respondents entered into agreements by which the 4th Respondent was to undertake a feasibility study, financing was sought from the Government of China and the project undertaken as a government-to-government project.

Two commercial contracts were signed between the Governments for the construction of the SGR line and for the supply and installation of facilities, locomotives and rolling stock. The 4th Respondent was then awarded the contract to construct the civil works and thereafter to supply the facilities, locomotives and rolling stock.

The Petitioners alleged among other things, that the Respondents failed to comply with the law regarding procurement. It was the Petitioners’ case that the project was subject to competitive bidding but had instead been single sourced. Further projects funded through loans and grants were not exempt from competitive bidding or the provisions of the Public Procurement and Disposal Act. The Petitioners contended that the Respondents had failed to seek Parliament’s approval despite the SGR loan being public debt and therefore a charge on the Consolidated Fund. They also faulted the Respondents for not pursuing value for money in relation to the SGR, for failing to undertake an Environmental Impact Assessment (EIA) and failing to consult with key stakeholders of the project.

The Respondents refuted the Petitioners’ claims, including that they had not complied with the Public Procurement and Disposal Act. They urged the court to expunge from the record the Petitioners’ evidence as they had failed to disclose the source of their information.

On 21st November 2014, the High Court ruled against the Petitioners and the petitioners appealed.

Prayers and Okoa Mombasa objectives

Okoa Mombasa membership was not involved in this case. However, similar to Okoa Mombasa’s objectives, the petitioners sought to reaffirm the rule of law and adherence to the Constitution that requires procurement to be fair, equitable, transparent, competitive and cost-effective.

Okoa Mombasa believes that action should be taken against public officers implicated in the unconstitutional procurement of the SGR.

High Court judgment

Judgment issued on 21 November 2014 included the following findings:

On whether the Petitioners’ case was supported by valid evidence, the court found that the evidence produced did not comply with the Constitution or the Evidence Act and was therefore expunged from the record. Further, in obtaining the documents, the Petitioners violated the Respondent’s right to privacy and the privacy of their communication.

The court found that the Public Procurement and Disposal Act did not apply to the procurement of the SGR project and therefore there was no violation of the law in that respect. In addition, the court held that Parliament had been involved in the budgeting of funds to be utilized in the SGR project by virtue of having approved an amendment to the law introducing the Railway Development Levy earmarked for the SGR construction.

It was the court’s finding that an Environmental Impact Assessment had been carried out, the Environmental Impact Assessment (EIA) License having been produced as evidence. The contention that the SGR project was detrimental to the environment lacked merit on this basis.

The court declined to delve into the issue of value for money, as the issue was outside the purview of the courts.

Court of Appeal judgment

The Court of Appeal issued its judgment issued on 19 June 2020:

The petitioners/appellants filed the present appeal being aggrieved by the High Court decision:

  • not to stop the construction of the Standard Gauge Railway on the allegation that its procurement and construction violated the Constitution and other laws,
  • to expunge from court records documents tendered by the petitioners and ruled to have been obtained illegally,
  • that there were no breaches of the Constitution in the procurement process and that Parliament had carried out its oversight role, giving financial approval for the project,
  • that the project was exempt from competitive bidding as it was a government-to-government project.

The Court of Appeal in its judgment held among other things:

  • that the conservatory orders sought were unavailable because by the time of hearing the appeal the railway was complete and operational;
  • the illegally acquired documents could not be admitted as evidence as this would contradict provisions of the Evidence Act, the Constitution and fair administration of justice. The decision of the High Court to expunge the documents from the court record was upheld.
  • that the procurement of the SGR project was not exempted from the provisions of section 6(1) of the Public Procurement and Disposal Act (repealed), and therefore Kenya Railways was bound to comply with the statute. Kenya Railways , as the procuring entity, failed to comply with, and violated provisions of article 227 (1) of the Constitution and sections 6 (1) and 29, of the Public Procurement and Disposal Act, 2005 in the procurement of the SGR project.
Share This